Question 139

What should a Development Team do if it realizes it has selected too much work after starting the Sprint?

    Correct Answer: B

    In Scrum, if the Development Team realizes they have selected too much work after starting the Sprint, they should engage with the Product Owner to adjust the scope. This might involve removing some work from the Sprint Backlog, which can help ensure the remaining work can be completed within the Sprint. It is better to adapt the Sprint scope early on rather than wait until the Sprint Review, where it may be too late to take corrective action. Adjusting the definition of 'Done' or adding more team members are not suitable practices within the Scrum framework.

Discussion
Edgecrusher77Option: D

No the B answer is mentionning the product backlog, not the sprint backlog. So in that case only D is acceptable in Scrum point of view

12monkeys

I agree

amogOption: B

B is correct