Which statement best describes the Sprint Review?
Which statement best describes the Sprint Review?
The Sprint Review is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next. This meeting aims to gather feedback and improve the next Sprint. It is not about congratulating or punishing the Development Team, checking for control, nor is it merely a demo for the entire organization.
D is correct answer, Can't be B - not everyone in the organisation needs to attend sprint review You don't punish the dev team and neither do you control them so not A or C.
B should be correct
Sprint review is not just a demo.
D is the correct answer