Exam PSM I All QuestionsBrowse all questions from this exam
Question 136

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should: (Choose the best answer.)

    Correct Answer: A

    In Scrum, the primary way to track progress is by inspecting the Increment at the Sprint Review. This aligns with the principles of transparency and inspection. The Scrum Master should explain to the IT manager that the team's progress should be evaluated based on the Increment delivered at the end of the Sprint, rather than through separate status reports. This helps maintain the focus on delivering value and adhering to Scrum practices.

Discussion
dagwoOption: C

C is the correct answer