PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 163


Which of the following is required in Scrum?

Show Answer
Correct Answer: A

In Scrum, the Sprint Retrospective is a required event. It takes place after each Sprint and serves as an opportunity for the team to inspect and adapt their process. While other elements like user stories, sprint burndown charts, and development team members answering questions during the daily scrum can be used in Scrum, they are not strictly mandated by the Scrum framework. Therefore, the Sprint Retrospective is the correct answer as it is explicitly required.

Discussion

1 comment
Sign in to comment
amogOption: A
Mar 10, 2021

A is the answer