Which of the following is required in Scrum?
Which of the following is required in Scrum?
In Scrum, the Sprint Retrospective is a required event. It takes place after each Sprint and serves as an opportunity for the team to inspect and adapt their process. While other elements like user stories, sprint burndown charts, and development team members answering questions during the daily scrum can be used in Scrum, they are not strictly mandated by the Scrum framework. Therefore, the Sprint Retrospective is the correct answer as it is explicitly required.
A is the answer