During the Sprint, the Development Team realizes they might not be able to finish all of the items in the Sprint Backlog.
What should happen?
During the Sprint, the Development Team realizes they might not be able to finish all of the items in the Sprint Backlog.
What should happen?
The Sprint length is a fixed time-box during which specific goals are meant to be achieved. If the Development Team realizes they might not be able to finish all items in the Sprint Backlog, they should adhere to the predefined Sprint time-box. This allows the team to continually learn and improve their estimation and effectiveness in future Sprints.
C is correct