What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?
What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?
The most appropriate action for the Scrum Master is to offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize the flow of value. The Product Owner is responsible for the Product Backlog, and it is crucial for them to understand how to prioritize work items effectively. Ordering the backlog by size or delegating the task does not address the underlying issue. Introducing assistance in understanding the value-based prioritization aligns with the Scrum framework principles.
C is the answer