PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 68


Adding more resources in Scrum will proportionally increase the value delivered.

Show Answer
Correct Answer: B

Adding more resources in Scrum does not proportionally increase the value delivered. In Scrum, the efficiency and value are derived from the team's ability to work together and iteratively improve processes and outcomes. Adding more resources can actually lead to increased coordination overhead, miscommunication, and dependencies which can hinder progress rather than help.

Discussion

1 comment
Sign in to comment
amogOption: B
Mar 9, 2021

B: False