PSM II Exam - Question 42


Steven is a Scrum Master of a Development Team that has members working in different cities and time zones. Organizing the Scrum events is time consuming and requires a lot of effort to set up and run. The Development Team proposes to only hold the Daily Scrum on Mondays.

Which two responses would be most appropriate from Steven? (Choose two.)

Show Answer
Correct Answer: AC

Steven, as a Scrum Master, must emphasize the importance of the Daily Scrum. Daily Scrums facilitate daily communication, help update the Sprint plan, and enable the team to self-organize towards the Sprint Goal. Coaching the team on these points and addressing their concerns about connectivity due to dispersed locations would be appropriate. Therefore, explaining the significance of daily meetings (option A) and helping the team understand the consequences of reduced communication frequency (option C) are the best responses.

Discussion

3 comments
Sign in to comment
Mi_WindsorOptions: AC
Aug 23, 2023

A and C

amogOptions: AC
Mar 9, 2021

A and C are correct

csmvvOptions: AC
Aug 18, 2023

A and C