Exam PSM I All QuestionsBrowse all questions from this exam
Question 48

Who is responsible for managing the progress of work during a Sprint?

    Correct Answer: B

    B

    Reference:

    https://www.aha.io/roadmapping/guide/release-management/what-is-a-sprint#:~:text=Who%20manages%20a%20sprint%3F,in%20sprint%20planning

    %20and%20implementation.&text=Responsible%20for%20maximizing%20the%20value,to%20accept%20stories%20as%20done

Discussion
Mi_WindsorOption: B

B is the correct answer

maverick_walkerOption: B

B is correct

okayheyOption: B

B, dev team is self-managing, Scrum master only ensures Scrum is correctly applied

Quinns_Option: A

A is the correct answer The Scrum Master is responsible for managing the progress of work during a Sprint. They guide and support the team to achieve their sprint goals and follow the Scrum framework.