PSM II Exam - Question 145


Every Development Team should have the competencies and skills needed to deliver a Done Increment in a Sprint.

Show Answer
Correct Answer: A

The statement is true. Every Development Team should indeed have the competencies and skills needed to deliver a Done Increment in a Sprint. Development Teams are designed to be self-organizing and cross-functional, meaning they possess all the skills necessary to create a working product increment without depending on external resources.