Question 76

Who is responsible for tracking the remaining work of the Sprint?

    Correct Answer: A

    In Scrum, it is explicitly stated that the Development Team is responsible for tracking the remaining work of the Sprint. They use tools and techniques such as the Sprint Burndown Chart to monitor their progress towards achieving the Sprint Goal. This responsibility ensures that the Development Team maintains ownership and accountability for their work.

Discussion
Jyoti1010Option: A

Developers

Mi_WindsorOption: A

A is correct, what about developer and PO