PSM I Exam - Question 76


Who is responsible for tracking the remaining work of the Sprint?

Show Answer
Correct Answer: A

In Scrum, it is explicitly stated that the Development Team is responsible for tracking the remaining work of the Sprint. They use tools and techniques such as the Sprint Burndown Chart to monitor their progress towards achieving the Sprint Goal. This responsibility ensures that the Development Team maintains ownership and accountability for their work.

Discussion

2 comments
Sign in to comment
Mi_WindsorOption: A
Aug 10, 2023

A is correct, what about developer and PO

Jyoti1010Option: A
Sep 26, 2023

Developers