Who is responsible for tracking the remaining work of the Sprint?
Who is responsible for tracking the remaining work of the Sprint?
In Scrum, it is explicitly stated that the Development Team is responsible for tracking the remaining work of the Sprint. They use tools and techniques such as the Sprint Burndown Chart to monitor their progress towards achieving the Sprint Goal. This responsibility ensures that the Development Team maintains ownership and accountability for their work.
Developers
A is correct, what about developer and PO