Question 70

Steven, who is a Scrum Master, on one of the Scrum Teams has approached you asking for advice. Their Daily Scrum requires more than 15 minutes and the team has suggested dividing themselves into two separate teams in order to stay within the time box.

As another Scrum Master, what would be the best response?

    Correct Answer: B

    Disagreeing is the best response because the root cause of the Daily Scrum exceeding 15 minutes may not necessarily be that the team is too big. It is important to identify and address the actual issue causing the extended time rather than immediately suggesting to divide the team. Potential causes such as communication problems, lack of focus, or ineffective time management during the Daily Scrum should be examined and corrected.

Discussion
amogOption: C

Yes, should be C