PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 73


Steven is a Scrum Master for three Scrum Teams building the same product and working from the same Product Backlog. Management wants to standardize how velocity is calculated across all three teams in order to identify which teams are high performing and which teams need more support.

What would be the best two responses Steven could provide to management? (Choose two.)

Show Answer
Correct Answer: AD

Velocity is an internal measure for the Scrum Team and does not have a direct relationship with the amount of value produced. It is a tool for the team to use in planning their work and assessing their capacity. Standardizing velocity across teams will not accurately measure the value delivered since it is unique to each team's context and cannot be compared directly. Therefore, stating that there is no direct relationship between velocity and value and emphasizing that velocity is an input for Sprint Planning unique to each team are the best responses.

Discussion

2 comments
Sign in to comment
amogOptions: AD
Mar 9, 2021

Yes, agree A and D

nhungnt184Options: AD
Apr 21, 2021

A and D.