Multiple Scrum Teams working on the same project must have the same Sprint start date.
Multiple Scrum Teams working on the same project must have the same Sprint start date.
Multiple Scrum Teams working on the same project do not need to have the same Sprint start date. The Scrum Guide does not mandate synchronized Sprint dates; it allows teams the autonomy to manage their Sprint schedules independently as long as they collaborate effectively and meet the project goals. Therefore, the correct answer is False.
B, because there is no must have
saw the question in PSM Exam
and the answer was False?
Was the answer true or false please?
Not required but recommended. So answer is B.
Teams can have different start and end date for their respective sprint.Sprint are desired to be aligned.for example one team can have a sprint that is 2 week long and another team working on same project can have a sprint that is 4 week long.
B false
https://www.scrum.org/forum/scrum-forum/43558/multiple-scrum-teams-must-use-same-sprint-start-date-same-product not crystal clear, but probably false
Answer is B. False
In the book "Scrum and Xp from the trenches" henrik kniberg on the page 103 it is mentioned that " it would be much better to synchronize the sprints " http://wwwis.win.tue.nl/2R690/2019-2020_Q1/doc/ScrumAndXpFromTheTrenchesonline07-31.pdf
"must have" therefore it is only a recommendation but not a must - B is correct.