PSM I Exam QuestionsBrowse all questions from this exam

PSM I Exam - Question 63


Multiple Scrum Teams working on the same project must have the same Sprint start date.

Show Answer
Correct Answer: B

Multiple Scrum Teams working on the same project do not need to have the same Sprint start date. The Scrum Guide does not mandate synchronized Sprint dates; it allows teams the autonomy to manage their Sprint schedules independently as long as they collaborate effectively and meet the project goals. Therefore, the correct answer is False.

Discussion

8 comments
Sign in to comment
DannyDXOption: B
Feb 17, 2021

B, because there is no must have

ainaoshokoya
May 2, 2020

saw the question in PSM Exam

unkn0wn4
May 11, 2020

and the answer was False?

Pebo
Jan 4, 2021

Was the answer true or false please?

Rz_rahgozarOption: A
Oct 30, 2020

In the book "Scrum and Xp from the trenches" henrik kniberg on the page 103 it is mentioned that " it would be much better to synchronize the sprints " http://wwwis.win.tue.nl/2R690/2019-2020_Q1/doc/ScrumAndXpFromTheTrenchesonline07-31.pdf

Hershey999
Dec 9, 2020

"must have" therefore it is only a recommendation but not a must - B is correct.

Anjani2020Option: B
Feb 7, 2021

Answer is B. False

aam1972Option: B
Apr 8, 2022

https://www.scrum.org/forum/scrum-forum/43558/multiple-scrum-teams-must-use-same-sprint-start-date-same-product not crystal clear, but probably false

Mi_WindsorOption: B
Aug 10, 2023

B false

Jyoti1010Option: B
Sep 26, 2023

Teams can have different start and end date for their respective sprint.Sprint are desired to be aligned.for example one team can have a sprint that is 2 week long and another team working on same project can have a sprint that is 4 week long.

CopyKingOption: B
Nov 25, 2023

Not required but recommended. So answer is B.