Exam PSM I All QuestionsBrowse all questions from this exam
Question 63

Multiple Scrum Teams working on the same project must have the same Sprint start date.

    Correct Answer: B

    Multiple Scrum Teams working on the same project do not need to have the same Sprint start date. The Scrum Guide does not mandate synchronized Sprint dates; it allows teams the autonomy to manage their Sprint schedules independently as long as they collaborate effectively and meet the project goals. Therefore, the correct answer is False.

Discussion
DannyDXOption: B

B, because there is no must have

ainaoshokoya

saw the question in PSM Exam

unkn0wn4

and the answer was False?

Pebo

Was the answer true or false please?

CopyKingOption: B

Not required but recommended. So answer is B.

Jyoti1010Option: B

Teams can have different start and end date for their respective sprint.Sprint are desired to be aligned.for example one team can have a sprint that is 2 week long and another team working on same project can have a sprint that is 4 week long.

Mi_WindsorOption: B

B false

aam1972Option: B

https://www.scrum.org/forum/scrum-forum/43558/multiple-scrum-teams-must-use-same-sprint-start-date-same-product not crystal clear, but probably false

Anjani2020Option: B

Answer is B. False

Rz_rahgozarOption: A

In the book "Scrum and Xp from the trenches" henrik kniberg on the page 103 it is mentioned that " it would be much better to synchronize the sprints " http://wwwis.win.tue.nl/2R690/2019-2020_Q1/doc/ScrumAndXpFromTheTrenchesonline07-31.pdf

Hershey999

"must have" therefore it is only a recommendation but not a must - B is correct.