Exam PSM II All QuestionsBrowse all questions from this exam
Question 33

During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item 'done'. Some say it is a part of the Definition of Done and others say it isn't. Steven, the Scrum Master, observes a debate forming and members beginning to take sides.

What is the best action for Steven to take?

    Correct Answer: C

    As a Scrum Master, it is important to act as a facilitator who helps the team resolve conflicts and improve their processes collaboratively. Facilitating a session where all members of the Scrum Team discuss the Definition of Done allows the team to address the conflict directly, refine their understanding, and reinforce effective collaboration. Additionally, coaching the team on the value of resolving conflicts and understanding that they are a natural part of teamwork promotes a healthy team dynamic and continuous improvement.

Discussion
lenanguyen89Option: C

C I think

OMG4567Option: C

C is correct

LuckyAroOption: A

I don't think the SM has the authority to refine the "Definition of Done"

OMG4567

I read the question different... I think the SM helps the team refine the DoD.

Mi_WindsorOption: C

C is the correct answer