Exam PSM I All QuestionsBrowse all questions from this exam
Question 68

What is the timebox for the Sprint Planning event?

    Correct Answer: B

    B

    Reference:

    https://www.thescrummaster.co.uk/scrum/the-sprint-planning-event-agreeing-priorities-and-planning-the-work/#:~:text=The%20Scrum%20Guide%

    20advises%20that,Planning%20event%20will%20be%20shorter

Discussion
Jyoti1010Option: B

8 hours for 4 week long sprint.

Mi_WindsorOption: B

8 hours for sprint planning 4 weeks

Jerry84Option: B

“Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.”