When is it most appropriate for a Scrum Team to change the Definition of Done?
When is it most appropriate for a Scrum Team to change the Definition of Done?
The most appropriate time for a Scrum Team to change the Definition of Done is during the Sprint Retrospective. This meeting is specifically designed for the team to reflect on the past Sprint, review what went well, what could be improved, and make actionable plans for the next Sprint. Adjusting the Definition of Done during this time allows the team to continuously improve their processes and practices, ensuring that quality and completeness criteria are up-to-date and aligned with their goals.
Definitely D, I wonder why they are many wrong answers
D : When is it most appropriate for a Scrum Team to change the Definition of Done
During each sprint retrospective, the Scrum team plans how to improve the quality of the product by adapting the definition of "complete" appropriately."
D all the way
The Sprint Retrospective is the most appropriate time for the Development Team to reflect on their practices and processes. If the Development Team identifies opportunities for improvement or finds that the current Definition of Done is inadequate, they can propose changes to it during the Sprint Retrospective. This allows the team to continuously enhance their Definition of Done, align it with their evolving understanding and requirements, and ensure it effectively reflects the expected quality and completeness of their work. It is a valuable opportunity to refine and update the Definition of Done for future Sprints.
D Scrum guide
Answer - D (Sprint Retrospective)
D is correct
It's during the retrospective, after completing the Sprint, that the team can consider adjustments for future Sprints.
D although it is also by Refinement allowed. The Most appropiate Time ist The Sprint Retrospective.