As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)
If the Development Team recognizes that the workload is more than they can handle during Sprint Planning, they should take actions that align with Scrum principles. Ensuring that the Product Owner is aware and then monitoring progress allows for transparency and adaptation as required. Additionally, it is valid to remove or change selected Product Backlog items to make the workload manageable, demonstrating flexibility. Recruiting additional members or working overtime is against Scrum values as it disrupts the team's cohesion and sustainable pace, and canceling the Sprint entirely is an extreme measure that is not typically favored.
"Scope may be clarified and re-negotiated between the Product Owner and Development Team as more is learned." - Scrum Guide
B & D are correct
B,D are correct
answers : B & D
Scope of the sprint can be re-negotiated.
B and D are correct