Exam PSM I All QuestionsBrowse all questions from this exam
Question 172

Who determines how many Product Backlog items the Developers select for a Sprint? (Сhoose the best answer.)

    Correct Answer: C

    The Developers determine how many Product Backlog items they select for a Sprint. They are the ones who will be doing the work and are best suited to understand their capabilities and the amount of work they can commit to within the Sprint.

Discussion
Jyoti1010Option: C

Developers pull items from product backlog.