Question 128

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog.

However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

    Correct Answer: A, B

    The Product Owner in Scrum is responsible for maximizing the value of the product resulting from the work of the Development Team. This includes ensuring that the most valuable functionality is produced first, aligning with the backlog prioritization process to meet business objectives. Additionally, the Product Owner interacts with stakeholders to gather feedback and understand their needs, ensuring the product delivers value to the end users.

Discussion
amogOptions: AB

A and B

Jyoti1010Options: AB

A and B

Jyoti1010

Product owner is a value maximizer.

ObeObeObeOptions: BD

I am saying no to A, they do not pick which work is done first.

xcjxcjOptions: AB

D is wrong, product owner does not write use cases, they even don't write user stories they just manage. A is correct, every sprint should produce those highest value functionality.

Jyoti1010

They do not pick but product owner is responsible for ordering the product backlog.