PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 135


Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?

Show Answer
Correct Answer: B

If the Development Team determines that it will not be able to finish the complete forecast, the correct approach is to adjust the selected work for the Sprint. This adjustment should involve the Product Owner and the Development Team. The Product Owner is responsible for prioritizing the Product Backlog and thus must be involved in deciding which tasks to move, while the Development Team provides a realistic assessment of their workload and capacity.

Discussion

1 comment
Sign in to comment
amogOption: B
Mar 10, 2021

B is the answer