Exam PSM II All QuestionsBrowse all questions from this exam
Question 135

Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?

    Correct Answer: B

    If the Development Team determines that it will not be able to finish the complete forecast, the correct approach is to adjust the selected work for the Sprint. This adjustment should involve the Product Owner and the Development Team. The Product Owner is responsible for prioritizing the Product Backlog and thus must be involved in deciding which tasks to move, while the Development Team provides a realistic assessment of their workload and capacity.

Discussion
amogOption: B

B is the answer