Correct Answer: A, B, CHolding the Daily Scrum less frequently would raise several concerns. First, impediments would be raised and resolved more slowly, which could hinder the team's progress and ability to meet the Sprint Goal. Second, opportunities to inspect and adapt the Sprint Backlog would be reduced, impeding the team's ability to effectively respond to change and optimize their work. Third, less frequent sharing of progress information would make the Sprint plan more inaccurate and reduce transparency over progress toward the Sprint Goal, potentially causing misalignment within the team. These issues cumulatively increase the risk of the team deviating from their objectives and reduce their ability to adjust promptly to any challenges or changes.