Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.
Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.
Multiple Scrum Teams working from the same Product Backlog do not necessarily need to have the same Sprint start dates. The key aspect is that they should be able to integrate their shippable increments effectively at the end of their Sprints, regardless of when those Sprints start.
B. False