Exam PSM II All QuestionsBrowse all questions from this exam
Question 159

Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

    Correct Answer: B

    Multiple Scrum Teams working from the same Product Backlog do not necessarily need to have the same Sprint start dates. The key aspect is that they should be able to integrate their shippable increments effectively at the end of their Sprints, regardless of when those Sprints start.

Discussion
amogOption: B

B. False