PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 159


Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.

Show Answer
Correct Answer: B

Multiple Scrum Teams working from the same Product Backlog do not necessarily need to have the same Sprint start dates. The key aspect is that they should be able to integrate their shippable increments effectively at the end of their Sprints, regardless of when those Sprints start.

Discussion

1 comment
Sign in to comment
amogOption: B
Mar 10, 2021

B. False