Question 119

A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

    Correct Answer: D

    The Scrum Master should begin facilitating productive and useful Sprint Retrospectives. One of the key responsibilities of the Scrum Master is to ensure that the Scrum framework is understood and enacted properly. The Sprint Retrospective is a crucial part of the Scrum process as it helps the team to reflect on the past sprint and improve processes and practices. It is not optional, and the Scrum Master must guide the team to understand its importance and value.

Discussion
hiepnb97Option: D

Scrum Master "They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization."

emelbaOption: D

scrum events are sacred

Jyoti1010Option: D

All scrum events are mandatory