Exam PSM II All QuestionsBrowse all questions from this exam
Question 103

A Scrum Master teaches those who are interested in the Development Team's progress that progress in Scrum comes from inspecting an Increment at the Sprint

Review.

    Correct Answer: A

    Progress in Scrum is indeed measured by inspecting an Increment at the Sprint Review. The Sprint Review is an event in Scrum where the Scrum Team and stakeholders inspect the Increment to assess progress towards the Sprint Goal and overall project objectives. Therefore, the statement that progress in Scrum comes from inspecting an Increment at the Sprint Review is true.

Discussion
amogOption: A

A. True