Question 38

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

    Correct Answer: A, B, F

    The Daily Scrum is essential for maintaining regular and timely communication within the Scrum team. It's an opportunity to inspect and adapt the Sprint Backlog each day, ensuring the team stays on track and any necessary adjustments are made promptly (loss of this opportunity would be a concern). Impediments need to be identified and addressed quickly to prevent delays in progress (slower resolution of impediments would be problematic). Additionally, without daily updates, the Sprint plan may become inaccurate, leading to potential misalignment with the Sprint's goals.

Discussion
sujoOptions: ABF

ABF is correct

kalguthorOptions: ABC

I think it's ABC

Pancogito

C - for sure is not good answer

Tianee

Why not? Isn't one of the advantages of Agile is to be have to provide "in time" reporting?

aam1972

PO and SM do not partecipate to the Daily Scrum unless they partecipate as developers

Jyoti1010Options: ABF

If the impediment are raised and resolves slowly (option B) that sprint plan to achieve sprint goal will become inaccurate (Option F). So option A,B and F are correct in my opinion.

Jyoti1010Options: ABF

Option AB and F are correct.

dandirindanOptions: ABF

makes sense

Edgecrusher77Options: ABF

Answers are ABF