PSM I Exam - Question 53


The CEO asks the Development Team to add a `very important` item to a Sprint that is in progress. What should the Development Team do?

Show Answer
Correct Answer: C

When a request is made by the CEO to add a very important item during an ongoing Sprint, it is crucial to follow the Scrum framework. The correct course of action is to inform the Product Owner, as the Product Owner is responsible for managing the Product Backlog and prioritizing work items. The Product Owner will then work with the CEO to assess the priority and importance of the new item and determine the appropriate course of action without disrupting the Development Team's focus and workflow.

Discussion

6 comments
Sign in to comment
Deck80Option: C
Feb 18, 2021

Answer is C, but in the updated version of the question (Scrum open assessment) the right answer is: "Inform the other members of the Scrum Team so the team can decide what to do. "

abenomarOption: C
Nov 21, 2020

Correct answer : C According to the scrum guide, The Product Owner may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item’s priority must address the Product Owner.

Mi_WindsorOption: C
Aug 10, 2023

C is correct

CopyKingOption: C
Nov 25, 2023

The CEO doesn’t tell the scrum team how to Do their job. C is the correct answer.

okayheyOption: C
Mar 29, 2024

Dev team is self-managing, the CEO doesn't dictate what they do.

maverick_walkerOption: C
Apr 29, 2024

C is correct