PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 188


When scaling Scrum it is important to have multiple Scrum Teams working from one Product Backlog.

Show Answer
Correct Answer: A

When scaling Scrum, it is important to have multiple Scrum Teams working from one Product Backlog to ensure alignment on the product vision and priorities. This single Product Backlog helps to minimize dependencies and ensure that all teams are working toward the same overall goals and deliverables.

Discussion

2 comments
Sign in to comment
TimmbuktuOption: A
Jul 5, 2024

Clearly it is A...

OMG4567Option: A
Jul 22, 2024

Clearly A: One product one backlog