Exam PSM II All QuestionsBrowse all questions from this exam
Question 165

What are typical Product Owner activities during Sprint 0?

    Correct Answer: E

    There is no such thing as Sprint 0 in Scrum terminology. Scrum defines a sprint as a time-boxed period in which a potentially shippable product Increment is created. The concept of Sprint 0, which might be used in some contexts to refer to preparation activities before the first official sprint, is not a formal part of Scrum. Therefore, there are no typical Product Owner activities specifically tied to Sprint 0.

Discussion
amogOption: E

E is correct

Edgecrusher77Option: E

E - No such thing as Sprint 0