Exam PSM II All QuestionsBrowse all questions from this exam
Question 6

At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being built. The current state of the product is not as expected and will require additional Sprints and more budget than originally anticipated at the start of the project.

What factors may have led to this? (Choose three.)

    Correct Answer: A, B, E

    Several factors could have led to the internal sponsors' dissatisfaction with the product's progress. First, the Product Owner may not have engaged with the sponsors frequently enough, failing to keep them updated on the project's progress and thus leading to misaligned expectations. Second, sponsors may not have taken advantage of Sprint Reviews to engage, inspect, and evaluate progress effectively, missing opportunities for course correction. Third, lack of transparency within the Scrum process, which is essential for open communication and alignment, may have contributed to the misunderstanding. The Scrum Master is responsible for fostering this transparency, which helps ensure that all stakeholders are aware of the current project status and any issues that might arise.

Discussion
Mi_WindsorOptions: ABE

ABE are correct

MYAT_T0TOptions: ABE

A B E correct

AgileSlyOptions: ABC

I would have said A, B, C

Mi_Windsor

C cannot be correct as that will be when you have a traditional waterfall project

lenanguyen89Options: ABC

A B C are correct.