PSM II Exam QuestionsBrowse all questions from this exam

PSM II Exam - Question 6


At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being built. The current state of the product is not as expected and will require additional Sprints and more budget than originally anticipated at the start of the project.

What factors may have led to this? (Choose three.)

Show Answer
Correct Answer: ABE

Several factors could have led to the internal sponsors' dissatisfaction with the product's progress. First, the Product Owner may not have engaged with the sponsors frequently enough, failing to keep them updated on the project's progress and thus leading to misaligned expectations. Second, sponsors may not have taken advantage of Sprint Reviews to engage, inspect, and evaluate progress effectively, missing opportunities for course correction. Third, lack of transparency within the Scrum process, which is essential for open communication and alignment, may have contributed to the misunderstanding. The Scrum Master is responsible for fostering this transparency, which helps ensure that all stakeholders are aware of the current project status and any issues that might arise.

Discussion

4 comments
Sign in to comment
Mi_WindsorOptions: ABE
Jul 19, 2023

ABE are correct

lenanguyen89Options: ABC
May 23, 2023

A B C are correct.

AgileSlyOptions: ABC
Jun 19, 2023

I would have said A, B, C

Mi_Windsor
Jul 19, 2023

C cannot be correct as that will be when you have a traditional waterfall project

MYAT_T0TOptions: ABE
Mar 28, 2024

A B E correct