PSM I Exam - Question 46


Which of these may a Development Team deliver at the end of a Sprint?

Show Answer
Correct Answer: C

At the end of a Sprint, a Development Team should deliver an increment of working software that meets the Definition of Done (DoD). The increment must be potentially shippable, meaning it has been fully integrated, tested, and is in a usable condition. This ensures that the product increment is of high quality and can be released to customers if needed.