Exam PSM II All QuestionsBrowse all questions from this exam
Question 183

At the seventh Sprint Review, the stakeholders seem disappointed and angry. When asked about it, they say the product being built will not meet their needs and will cost more than they anticipated spending. What factors may have led to this? (Choose three.)

    Correct Answer: B, C, F

    One major factor is the lack of transparency, which falls under the responsibility of the Scrum Master. If transparency is not ensured, stakeholders will not have a clear understanding of the project's progress. Another critical issue is the Product Owner not interacting frequently with stakeholders; this role is essential for communicating the project's development and ensuring the product meets their needs. Lastly, if stakeholders do not actively engage in Sprint Reviews, they miss opportunities to inspect and provide feedback, leading to a disconnect between their expectations and the actual product. These gaps in communication and engagement can lead to dissatisfaction with the product and unexpected costs.

Discussion
Kapello10Options: BCF

BCF is correct