A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)
In a Scrum framework, the Development Team and the Scrum Master collaborate closely, so consulting with the Development Team can provide insights and assistance in resolving impediments. Prioritizing the list of impediments ensures that the most critical issues are addressed first, maximizing the team's efficiency and productivity. Alerting management to the impediments and their impact provides additional support and resources that may be necessary to resolve complex issues that the Scrum Master and Development Team alone cannot handle. Option C, arranging a triage meeting with all project managers, is not applicable as there is no role of project manager in Scrum.
ABD are correct
It was easy to answer this because there is no role called Project Manager in scrum, so C is definitely eliminated.
ABD are correct