Question 171

Who is responsible for collaboration with stakeholders? (Choose the best answer.)

    Correct Answer: A

    The Scrum Team is collectively responsible for collaborating with stakeholders. This includes the Product Owner, Scrum Master, and Developers. The Scrum Team works together to ensure a clear understanding of stakeholder needs and priorities, thus facilitating effective communication and collaboration.

Discussion
UppersquareCapitalOption: A

Answer A - The Scrum team is responsible for all product-related activities from Stakeholder collaboration, verification, maintenance, operation, experimentation, R&D, and anything else that might be required.