At the end of PI Planning after dependencies are resolved and risks are addressed, a confidence vote is taken. What is the default method used to vote?
At the end of PI Planning after dependencies are resolved and risks are addressed, a confidence vote is taken. What is the default method used to vote?
At the end of PI Planning, the process typically involves a vote by each team to gauge their confidence, followed by a collective vote by every person in the train. This ensures both team-level and individual-level validation of confidence in the plan.
first voting within the team, then for the train
A, ist die richtige Antwort.
Each team conducts a vote using their fingers (fist of five) or a digital tool for remote events. Once each team has voted, it’s repeated for the entire ART, with everyone expressing their confidence in the collective plan