During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent?

    Correct Answer: B

    ROAM stands for Resolved, Owned, Accepted, Mitigated. These are the four categories used to classify risks during the final plan review in program management. 'Resolved' means the risk has been handled and is no longer a concern. 'Owned' indicates a stakeholder has taken responsibility for managing the risk. 'Accepted' signifies that the risk is acknowledged as inherent and its potential impact is accepted. 'Mitigated' means actions have been taken to reduce the risk's impact or likelihood. Therefore, the correct option is the one that lists these terms accurately.

Discussion
ghettosOption: A

The correct answer shall be "A." - Resolved - Owned - Accepted - Mitigated

Nego91Option: A

Resolved Owned Accepted Mitigated

Perica17Option: A

A https://scaledagileframework.com/planning-interval/

Mafer1980Option: A

It should be A

APTLYTiCOption: A

It should be A

MickeyMaxOption: A

Answer is A

ZjostOption: A

Answer A

sj2044Option: A

Resolved, Owned, Accepted, Mitigated

ThaaoleeOption: D

D is the right answer