Question 4

During the PI Planning event, when are planning adjustments agreed upon?

    Correct Answer: C

    Planning adjustments during the PI Planning event are agreed upon during the management review and problem-solving. This is the stage where management reviews the draft plans, identifies challenges like scope, resource constraints, and dependencies, and negotiates necessary changes to ensure a viable and feasible final plan.

Discussion
blue_moonOption: C

https://scaledagileframework.com/pi-planning/ Management review and problem-solving – Draft plans likely present challenges like scope, people and resource constraints, and dependencies. During the problem-solving meeting, management may negotiate scope changes and resolve other problems by agreeing to various planning adjustments. © Scaled Agile, Inc. Include this copyright notice with the copied content. Read the FAQs on how to use SAFe content and trademarks here: https://scaledagile.com/about/about-us/permissions-faq/ Explore Training at: https://scaledagile.com/training/calendar/

blue_moon

Option C is the correct answer

ashrmjoshiOption: C

option C

WhyRamyOption: C

C. During the management review and problem-solving