What data does the system require to determine the safety stock during automatic reorder point planning? (Choose three.)
What data does the system require to determine the safety stock during automatic reorder point planning? (Choose three.)
To determine the safety stock during automatic reorder point planning, the system requires the replenishment lead time, the service level, and the mean absolute deviation. The replenishment lead time is necessary to understand how long it takes to receive new stock after an order is placed. The service level indicates the desired probability of not running out of stock, and the mean absolute deviation measures the forecast error to adjust the safety stock accordingly. The storage costs code and the minimum and maximum stock levels are not directly involved in calculating the safety stock.
ACD To determine the safety stock, the system requires the following data: ● RLT ● Service level (factor according to standard distribution) ● Mean absolute deviation Reference: S4525 Consumption Based Planning and Forecasting in SAP S/4HANA l Pg. 124
ACD son las correcta.
The following values are important for defining the reorder point: Safety stock Average consumption Replenishment lead time The following values are important for defining the safety stock: Past consumption values (historical data) or future requirements Vendor/production delivery timelines Service level to be achieved Forecast error, that is, the deviation from the expected requirements