You have agreed on a value contract with a supplier for packaging. The exact materials and their purchase prices are NOT specified until the release orders.
Which item category must you use when creating the contract?
You have agreed on a value contract with a supplier for packaging. The exact materials and their purchase prices are NOT specified until the release orders.
Which item category must you use when creating the contract?
When creating a value contract where the exact materials and their purchase prices are not specified until the release orders, you should use the item category 'M (Material unknown)'. This category allows you to create contract items without specifying the material number, which aligns with the requirement that exact materials are not specified.
Correct answer is C
if value and quantity are unknown then correct answer would have been option C but since in this question it is clearly stated that material is NOT specified therefore correct option is D(M (Material unknown) )
Item category W Recommended for materials belonging to the same material group but with different prices.
okay, yes... but... When creating a value contract where the exact materials and their purchase prices are not specified until the release orders, you must use item category: M (Material unknown)
why is it not C? material group is packaging, no?
When creating a value contract where the exact materials and their purchase prices are not specified until the release orders, you must use item category: D. M (Material unknown)1 Item category M is for entering contract items without specifying the material number1. It is recommended for similar materials with the same price but with differing material numbers1
I am looking at these answer's and so far they are looking good. It seems reliable. I have compared them from the SAP Hub as well.
Has anyone given attempt with this? I want to know are they authentic?
Yes, to your question. I am still going through the questions but so far they are looking good. I've done several comparisons and they are correct.
te refieres a todas las preguntas o a esta?
item Category M = Material Unknown item Category W = Value & Quantity Unknow
Material Unknown only in this case.