c_ts452_2021 Exam - Question 20


You want to identity the spend of purchase orders that do NOT have a contract reference, although an existing contract could have been used.

What key performance indicator (KPI) provides this information?

Show Answer
Correct Answer: AB

The key performance indicator that identifies the spend of purchase orders that do not have a contract reference, although an existing contract could have been used, is 'Contract leakage'. This KPI specifically measures the amount of spend that occurs outside of established contracts, which aligns with the scenario described in the question.

Discussion

5 comments
Sign in to comment
praveenhp4Option: B
Feb 3, 2023

B is the correct answer

praveenhp4Option: B
Feb 3, 2023

B is the correct answer

AFM123Option: B
May 6, 2023

is the correct answer

ErLaLaOption: B
May 11, 2023

You can identify the spend of purchase orders that do not have a contract reference, although an existing contract could have been used. As a purchaser, you are interested in finding out the related net value. You can use Contract Leakage to find out the amount of purchases made without considering existing contracts.

SAPierOption: C
May 3, 2023

It has a contract. So the contract is leaking...Duh!

SAPier
May 3, 2023

I meant B...Ehm, sorry! XD