Question 22

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? (Choose two.)

    Correct Answer: C, D

    During an MRP Live planning run for externally procured materials, planned orders and purchase requisitions are typically created. A planned order is a proposed production order or an external procurement order, which serves as a request to procure material at a specific time. A purchase requisition is a formal request to procure a specific quantity of material or a service. Purchase orders and delivery schedule lines, on the other hand, are not directly created during the MRP Live planning run.

Discussion
ChillSealOptions: CD

It might be C and D: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/fe39e10a9a864a8f8dc9537704f0fa13/7cbbb853dcfcb44ce10000000a174cb4.html?q=Procurement%20Proposal&locale=en-US