Certified Business Analyst Exam QuestionsBrowse all questions from this exam

Certified Business Analyst Exam - Question 92


Universal Containers is focused on an initiative to streamline its channel management processes. Due to the level of complexity, the business analyst (BA) will gather and document the key points in preparation to build a more detailed process map.

Which diagram should the BA use in this case?

Show Answer
Correct Answer: AB

A SIPOC (Suppliers, Inputs, Process, Outputs, Customers) diagram should be used in this case. This diagram identifies all the key elements of a process such as suppliers, inputs, the core processes, outputs, and customers, which is essential for preparing to build a more detailed process map. It helps in defining the scope of a complex process and is instrumental in streamlining channel management processes.

Discussion

1 comment
Sign in to comment
cvngoOption: B
Jun 19, 2024

A SIPOC map shows the key elements of a process such as Suppliers, Inputs, Process, Outputs, and Customers. This map is ideal when you want to identify the key points in a process as a way to prepare for a more detailed process map. It is also great when you need to define the scope of a complex process. https://trailhead.salesforce.com/content/learn/modules/process-mapping-for-business-analysts/speak-the-process-mapping-language

cvngo
Jun 19, 2024

So it should be B