Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 233

The 'capability to deliver health and safety training' has been delivered and accepted. The project manager has produced the end stage report and has recommended that the project should be closed because it is complete.

Is this an appropriate application of the 'progress' theme, and why?

    Correct Answer: A

    The correct application of the 'progress' theme requires that when the project product has been delivered and accepted, the project should be closed. The end stage report indicates the completion and acceptance of the project product, confirming that the project has met its objectives. Therefore, the project manager's recommendation to close the project because it is complete is appropriate as the project product has been delivered and accepted.

Discussion
ravi_awsOption: B

Yes, because the end stage report should recommend the next steps to take to the project board