PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 233


The 'capability to deliver health and safety training' has been delivered and accepted. The project manager has produced the end stage report and has recommended that the project should be closed because it is complete.

Is this an appropriate application of the 'progress' theme, and why?

Show Answer
Correct Answer: A

The correct application of the 'progress' theme requires that when the project product has been delivered and accepted, the project should be closed. The end stage report indicates the completion and acceptance of the project product, confirming that the project has met its objectives. Therefore, the project manager's recommendation to close the project because it is complete is appropriate as the project product has been delivered and accepted.

Discussion

1 comment
Sign in to comment
ravi_awsOption: B
Oct 6, 2023

Yes, because the end stage report should recommend the next steps to take to the project board