Question 329

Which statement applies to the Quality standards section?

    Correct Answer: D

    The Quality standards section should outline the standards for maintaining the quality of both the project's products and processes. Adding 'PRINCE2 change control procedures will be used to manage any changes to baselined products' ensures there is a structured approach to managing changes, maintaining the integrity and quality of the project's outputs. This is a crucial aspect of quality management as it helps to control changes systematically.

Discussion
a0b3febOption: C

It is C

ravi_awsOption: D

The correct answer is D. Add ‘PRINCE2 change control procedures will be used to manage any changes to baselined products’. The Quality standards section should include the standards that will be applied to the project products and processes. Entry 4 is relevant because it specifies the industry standards for the outsourced services. Entry 5 is also relevant because it specifies the MFH document standards for the project documentation. Entry C is not relevant because it is already covered by the Roles and responsibilities section, where it states that the DIT will check the employment contracts. Entry D is relevant because it specifies how the project will manage any changes to the baselined products, which is an important aspect of quality management. Therefore, entry D should be added to the Quality standards section.