Question 184

What products will be impacted by this change?

    Correct Answer: A

    All of the project's products created so far will be impacted. This is because a change in the configuration management procedure requires revisiting and potentially updating all the existing products to ensure they comply with the new procedure. This would encompass all documents, plans, reports, or other deliverables that have been produced up to this stage of the project.

Discussion
ravi_awsOption: A

A. All of the project's products created so far. This is because the MFH Quality Manager will administer the configuration management procedure for the Restructuring project, and this procedure must comply with the MFH document control process. Therefore, all of the project's products created so far will need to be reviewed and updated to comply with the new configuration management procedure. This includes any documents, plans, reports, or other project deliverables that have been created up to this point.

watew

Duplicate Question 12, Topic 7