Identify the missing words in the following sentence.

If approved, an exception plan will replace the [?] and show the actions required to recover from the efficient of a tolerance deviation.

    Correct Answer: C

    An exception plan is a plan that replaces a stage plan, project plan, or team plan in case the original plan can no longer deliver the desired outcomes due to a tolerance deviation. In this sentence, the most appropriate word to complete the sentence is 'stage plan.' This is because an exception plan is most commonly used to replace a stage plan when there is a significant deviation from the accepted tolerance levels.

Discussion
jj0097Option: C

definitely C

hamed246Option: C

C is Correct Exception Plans can be used to replace Stage Plans and Project Plans, but not Team Plans.

Martin77Option: C

This is wrong! It should be C. stage plan: https://prince2.wiki/theme/plans/ reference from this link: Exception Plans can be used to replace Stage Plans and Project Plans, but not Team Plans.

El_CabronOption: C

It's C

kuku1789Option: C

Should be C