PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 310


Which 2 alternative actions apply to the proposed Executive for this project?

Show Answer
Correct Answer: BC

The 'Director of Finance Division' should be considered because she can ensure a cost-conscious approach to the project, enhancing value for money. Additionally, it is important to retain the current Executive if he possesses the right level of authority to control the strategic nature of the outsourcing project, as strategic control is critical for the success of such initiatives.

Discussion

2 comments
Sign in to comment
Pauly
Oct 1, 2020

Owing to the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being restructured will work with the external consultants who conducted the feasibility study to create the detailed design and specification.

ravi_awsOptions: BC
Oct 8, 2023

C. Retain because he has the right level of authority to be able to control the strategic nature of the Outsourcing project. B. Replace with ‘Director of Finance Division’ because she can ensure a cost-conscious approach to the project that gives value for money.