Which of the following is NOT an objective of Initiating a Project?
Which of the following is NOT an objective of Initiating a Project?
Initiating a Project involves defining what the project will achieve, understanding the scope, determining quality requirements, and establishing how progress will be monitored and controlled. Understanding the roles and responsibilities of the Project Management Team is typically established during the Starting Up a Project phase, making option B the correct choice as it is not an objective of the Initiating a Project phase.
B seems the most appropriate as the Project Management Team is designed and appointed during the Starting Up a Project process; but question is not so clear as also products and scope need to be to some extent understood in the Starting Up a Project process while compiling the Project Brief.
16.2 refers the below as an objective of 'Initiating a project process' The scope of what is to be done and the products to be delivered
Figure 16.1
B - Figure 14.1
B. Ref 16.2