Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 170

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

    Correct Answer: B

    The business justification must be reviewed throughout each stage of the project. This ensures that the project remains viable, continues to deliver value, and is aligned with business objectives. Regularly reviewing the business case helps in identifying any deviations early and allows for corrective actions to be taken timely. This approach aligns with the principles of continuous validation and consistent checks in project management methodologies.

Discussion
GetRajOption: D

Option D is correct. As per Prince2 Manual section 12.2 review the business justification when exceptions are raised (PRINCE2's continued business justification principle)

Mehan

agree D is the Correct answer

sohrabianiOption: C

D is not correct but when exception raise during checking it, the business justification will also be checked

peppeOption: D

D IS CORRECT. BAD QUESTION!!

Martin77Option: D

To meet the minimum requirements for applying the progress theme - this is the key to this tricky question. 12.2 in the prince manual states (review the business justification when exceptions are raised (PRINCE2's continued business justification principle) ) so D is the correct answer.

Wombat1987Option: D

I was confused at first but the correct answer is D. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7 Minimum requirements You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.

FarbodOption: D

D is correct "Review the business justification when exceptions are raised."

TommasoOption: B

B is correct

AgnesMOption: D

Answer D is correct as per section 12.2 in Prince 2 Manual.

MaximeHUOption: B

yes but also at each stages wich is more important.

TesteurtestOption: D

I was confused at first but the correct answer is D. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7 Minimum requirements You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.

RD27Option: B

Throughout each stage - Business Justification has to be verified

renzaOption: D

D is the right answer