PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 257


According to the minimum requirements for the plans theme, which type of plan is optional?

Show Answer
Correct Answer: D

A Team plan is optional according to the minimum requirements for plans theme. It is not always necessary in all projects, whereas Project plans, Stage plans, and Exception plans are generally deemed essential for managing different aspects and stages of a project.

Discussion

1 comment
Sign in to comment
ToyeebOption: C
May 4, 2024

Exception plan is out of necessity