Question 257

According to the minimum requirements for the plans theme, which type of plan is optional?

    Correct Answer: D

    A Team plan is optional according to the minimum requirements for plans theme. It is not always necessary in all projects, whereas Project plans, Stage plans, and Exception plans are generally deemed essential for managing different aspects and stages of a project.

Discussion
ToyeebOption: C

Exception plan is out of necessity